Planning & Budgeting

How Long Do Cabinets, Tile and Countertops Actually Take to Arrive?

About two weeks. That is the honest answer for most of what goes into a basement or a bathroom, and it holds well enough that I plan around it. Tile, engineered marble, standard cabinets, most flooring. The materials that break that rule break it badly though, and the bigger problem is one nobody expects: even when a lead time is short, your house usually has nowhere to put the material once it arrives.

Kitchen with extensive stained cabinetry, granite countertops and a mosaic tile backsplash, used to illustrate why cabinets are ordered first on a remodel.

Two Weeks Is the Working Baseline

Across the board, two weeks is what I see. Nobody at a supplier promised me that number and it is not printed on anything. It comes from what the last couple of years of ordering for jobs in Cache Valley have actually looked like, which makes it useful for planning and useless for arguing with.

Tile has come in inside a week. Tile has also taken three. Two weeks is where it lands most often, and that is the number I build a schedule against until a supplier tells me otherwise.

Our manufactured marble and engineered marble showers run about the same. Two weeks, sometimes stretching to three. Those are made to order, so the range is narrower than you would think.

Doors and Windows Are the Wild Card

Here the range stops being useful. I have had doors arrive in a week and a half. I have had the same product take six weeks.

What moves it has almost nothing to do with the product. It comes down to how busy the supplier happens to be the week you order. Walk in during a quiet stretch and you get the fast number. Walk in when every builder in the valley is placing orders and you get the slow one, on exactly the same door.

Nothing about your project changes that. You cannot pay it down or plan around it, and no supplier will quote you a range honestly enough to schedule against. It is the single least predictable thing I order.

Cabinets Can Move a Schedule by a Month

Standard cabinets run about two weeks, in line with everything else.

Semi custom is a different animal. Six weeks is normal. I have seen considerably longer. The moment a client wants a size, a finish, or a configuration that is not sitting in a catalogue, the clock changes character completely, and a two week assumption becomes a month and a half.

That gap almost never comes up during the selection conversation, because from the showroom floor the two options look like versions of the same thing. They are not the same thing to your schedule.

Order Cabinets First. Every Time.

If there is one operational rule worth taking from all of this, it is that cabinets get ordered before anything else.

They carry the longest realistic lead time, the most variability, and the most downstream work waiting on them. Countertops cannot be templated until cabinets are set. Plumbing trim waits on the counter. Backsplash waits on both.

Windows come second on that list, on any job carrying a real window package. A single slow window can hold up insulation, drywall, and everything that follows, which turns a supplier’s busy week into a month of your basement finishing timeline.

There is a second reason, and it comes down to where in the sequence a delay lands. Tile arriving late costs you a few days near the end, when the space is mostly built and there is other work to fill the gap. A cabinet arriving late holds the countertop template, which holds the countertop, which holds the plumbing trim and the backsplash behind it. One slow item at the front of a job multiplies through everything downstream. The same item at the back just sits there.

Why You Cannot Simply Order Everything Early

Everybody likes the idea of getting it all ordered and sitting on site before the first day. It is a sensible instinct and it is usually not available.

The limit is space. On a basement finish we are working inside somebody’s home, and there is rarely a spare room to fill with pallets. If a client does not have a garage they can give up for six weeks, we cannot stage the whole job in it. Even when they do, handing over the garage means two cars outside through a Cache Valley winter, and most people say no once they picture it.

So we order to a schedule instead. Material arrives close to the week it gets installed, which keeps the house livable and keeps thousands of dollars of tile out of a hallway where somebody will eventually put a foot through a box.

What can be staged early usually gets staged early. Small items, trim, fixtures in their boxes. The things that would actually buy you protection against a slow supplier are the bulky ones, and those are exactly the ones a family home has no room for.

Just in Time Works Until Something Slips

That approach handles most of a project without any drama. The exposure is obvious enough once you see it.

When material is scheduled to land the week it goes in, a supplier running two days late lands directly on your calendar. There is no buffer sitting in the garage to absorb it. The crew that was booked for Tuesday is on another job by Thursday, and now you are waiting on people rather than on product.

That is the trade. Storing everything up front costs you your house for a month and removes the risk. Ordering to schedule keeps your house and accepts the risk. On most jobs the second one is the only realistic option, so the honest thing is to say out loud that it carries a cost, and that projects run long for reasons like this more often than for dramatic ones.

Nothing Gets Ordered Until It Is Signed and Paid

One rule sits underneath every number on this page. We do not order material until the change order is signed and the deposit has been paid. That is absolute, and it is the same on every job we run.

So a two week lead time is really two weeks from the day you commit, not two weeks from the day we talked about it. A client in Providence took two weeks to sign off on flooring and some plumbing parts, then expected installation almost immediately after signing. The week of lead time still had to happen. It just happened with nothing else running alongside it, which is what turned a decision into a delay.

Your decision date plus the lead time is your install date. That equation does not have a third term, and both numbers in it are visible from the start. The first one belongs to you, which is why getting selections locked early matters more than most homeowners expect.

Start Planning Earlier Than Feels Necessary

If you think you might want a remodel, start planning as soon as the thought occurs to you. Not because the design takes long, and not to get you into a contract sooner.

The reason is that the supplier calendar is the one piece of this nobody controls. A project scoped in October and ordered in November hits a different set of lead times than the identical project ordered in March. Being early is the only lever you have on the part of the schedule that is genuinely out of everyone’s hands.

If you are planning a basement, kitchen or bathroom in Logan, North Logan, Providence, Smithfield, Hyde Park, Nibley or Hyrum and want a realistic sequence for your project, we can walk through it. You can request an estimate, read our published pricing, or look through projects we have finished.

Common Questions

How long do cabinets take to arrive?

Standard cabinets run about two weeks. Semi custom is commonly six weeks and can be considerably longer, so the difference between a catalogue configuration and a custom size or finish can move a schedule by a month.

What is a typical lead time for tile and countertops?

About two weeks is the working baseline in Cache Valley. Tile has arrived inside a week and has also taken three. Manufactured and engineered marble showers run about two weeks and sometimes stretch to three.

Why are door and window lead times so unpredictable?

They depend on how busy the supplier is the week you order rather than on the product. The same door has arrived in a week and a half and taken six weeks, with nothing different about the project.

Can I just order all my materials up front to avoid delays?

Usually not, because of storage. On a basement finish we are working inside your home and most families cannot give up a garage for six weeks, so material is ordered to arrive close to the week it is installed.

Does the lead time start when I choose the material?

It starts when the change order is signed and the deposit is paid, because we do not order material before that. Your decision date plus the lead time is your installation date.