ADU Planning & Design

How Long Does It Take to Build an ADU?

How long does it take to build an ADU? A garage or basement conversion runs three to five months from permit approval to completion. A detached unit runs six to ten months or more. That gap is almost entirely the work that happens before anything looks like a building, and permit review itself is a minimum of two to four weeks on either path. If you want to be living in it next year, the planning conversation starts this winter.

New home under construction, used to illustrate how long it takes to build an accessory dwelling unit.

Why a conversion is half the project

On a conversion, the structure already exists. No excavation, no footings, no foundation cure, no framing, no roof, no siding, no weather delay waiting for a dry week to get it dried in.

What is left is interior work, and interior work is predictable. Rough plumbing, rough electrical, HVAC, insulation, drywall, flooring, trim, cabinets, fixtures, paint. Each of those has a known duration and they stack in a known order.

Three to five months covers that sequence with inspections between the stages. The variability is mostly in material lead times and in how many trades are chasing the same calendar.

Why a detached unit takes twice as long

A detached ADU is a house. Small, but a house, and it goes through every stage a house goes through.

Excavation and site work. Footings and foundation, which then has to cure. Framing. Roofing. Windows and exterior doors. Siding. Only when all of that is standing and dry does the interior sequence start, and that interior sequence is roughly the same length as the entire conversion project.

Utilities add their own stretch. Water, sewer, power and gas have to reach a building that previously had none, which means trenching, inspections, and in some cases a utility company’s own schedule rather than yours.

Six to ten months is the published range and the top of it is not unusual.

Permitting is about the same either way

This surprises people who assume a conversion gets waved through. It does not.

Permit review runs a minimum of two to four weeks on both paths. You are adding a dwelling unit either way, which means plan review for the kitchen, the bathroom, the egress, the fire separation and the mechanical, plus whatever your city requires for the rental side.

Where the two differ is what happens before review. A detached unit needs a full set of drawings and usually engineering, and our published figure for architectural and engineering plans is $2,500 to $4,500. Getting those produced and coordinated is weeks of work that happens before the city has anything to look at.

An internal ADU has a legal advantage here rather than a speed advantage. Because state law makes it a permitted use in residential zones, you are not applying for a conditional use permit and you are not going to a public hearing. That removes a category of delay and a category of risk, which matters more than a couple of weeks.

The season decides your start date

This is the part that costs people a year when they miss it.

For anything involving excavation and a foundation, the ideal time to break ground in Cache Valley is April or May. You want the ground open and the concrete poured with the whole good season ahead of you, not a foundation going in during the first week of November.

Work backward from there. Design and permitting on a project with structural work takes a minimum of four to six weeks and eight to twelve weeks or longer when the design is complex. Add time to find a contractor, agree on scope, and get drawings produced. That puts the first conversation in November or December of the year before.

So if you are reading this in the fall and want a detached ADU next year, this is the month to start. Not spring. Spring is when the shovel goes in, and by then the planning should already be finished.

A conversion is far less seasonal, because the work is inside. That is a real and underrated advantage of the conversion path, and it means a conversion started in January is a perfectly sensible plan.

What actually causes the delays

Three things, in order of how often they bite.

Selections. Cabinets, tile, countertops and fixtures have lead times, and a decision that has not been made is a trade that cannot be scheduled. This is the most common cause of a project running long and it is the one entirely within your control.

Change orders. Each one adds a week or more, and they tend to arrive once somebody can walk the space and see it.

Inspection scheduling. You do not control the city’s calendar. A framing inspection that sits two days is two days nobody can cover the walls.

None of those are unusual. They are the reason a schedule carries float, and a contractor who gives you a date with no slack in it is telling you something about how they plan.

A realistic calendar for each path

For a conversion: four to eight weeks for design, drawings and selections, two to four weeks for permit review, then three to five months of construction. Call it six to eight months from first call to moving in.

For a detached unit: eight to twelve weeks or more for design, engineering and drawings, two to four weeks for permit review, then six to ten months of construction, weather permitting. Call it a year from first call, and more if the site is difficult.

That matches what we see on home additions, where the published figure from first call to final walkthrough is a minimum of six months for something straightforward and nine months to a year for something larger. See how long a home addition takes for the comparison.

Before you set a date

Decide which path you are on, because it is the difference between half a year and a full one. Confirm the project is allowed before you spend anything on drawings, which whether you can build an ADU on your lot covers. Then get your selections made early, since that is the delay you own.

For costs see the ADU cost guide and is $150,000 enough for an ADU. For permitting specifically, what permits you need in Cache Valley. To talk through timing on a specific property in Logan, Providence, Smithfield or anywhere in Cache Valley, request an estimate.